Construction to extend Coit Road to Rockhill Parkway and widen Westridge Boulevard is nearly done.[/caption]
1. Coit Road and Westridge Boulevard construction
Construction to extend Coit Road to Rockhill Parkway and widen Westridge Boulevard is nearly done. Coit Road will extend to four lanes, and Westridge Boulevard will widen to four lanes.
Timeline: June 2016-March 2017 Cost: $5.7 million Funding sources: city of Frisco, Collin County
[caption id="attachment_219588" align="alignright" width="199"]
Construction is about 85 percent complete to extend 4th Army Drive from Lebanon Road to the Stewart Creek Wastewater Treatment Plant.[/caption]
2. 4th Army Drive extension
Construction is about 85 percent complete to extend 4th Army Drive from Lebanon Road to the Stewart Creek Wastewater Treatment Plant. The new roadway, which is the first phase of the road project, will be two lanes.
The second phase of the project, to extend the road from the treatment plant to Timber Ridge Drive, is being designed.