Construction is almost finished on the first phase of 4th Army Drive.[/caption]
1. 4th Army Drive
Construction is almost finished on the first phase of 4th Army Drive to build a connection from Lebanon Road to the Stewart Creek West Wastewater Treatment Plant. Construction is about one-quarter through the second phase of the project to add a two-lane undivided roadway from the wastewater treatment plant to Timber Ridge Drive.
Timeline: July 2015-September 2017 (Lebanon Road to SCWWTP), July 2016-June 2018 (SCWWTP to Timber Ridge Drive) Cost: $3.2 million (Lebanon Road to SCWWTP), $11.4 million (SCWWTP to Timber Ridge Drive) Funding source: city of Frisco
[caption id="attachment_271544" align="alignright" width="220"]
Construction is more than half done on the first phase of the Dallas Parkway project.[/caption]
2. Dallas Parkway widening
Construction is more than half done on the first phase of the Dallas Parkway project to construct an additional lane on northbound and southbound frontage roads with intersection improvements at Warren Parkway and Lebanon Road. The second and third phases, which will add a lane on the northbound and southbound frontage roads at Eldorado and Panther Creek parkways, are still in the planning phase.
Timeline: January 2017-December 2018 (Warren Parkway and Lebanon Road), July 2018-TBD (Eldorado and Panther Creek parkways) Cost: $11.5 million (Warren Parkway and Lebanon Road), $7.5 million (Eldorado and Panther Creek parkways) Funding sources: city of Frisco, Collin County, Texas Department of Transportation