Want to know more about the latest development projects in Frisco? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.
Eyecare Partners: 5266 Independence Parkway, Ste. 150, Frisco
Type of work: New construction
Timeline: Feb. 15-May 26
Estimated cost: $450,000
McDonald's: 5615 Eldorado Parkway, Frisco
Type of work: renovation/alteration
Timeline: April 24-May 23
Estimated cost: $250,000
Bath & Body Works: 2601 Preston Road, Space 1042, Frisco
Type of work: renovation/alteration
Timeline: April 3-June 9
Estimated cost: $275,000
Hunan Chef: 9292 Warren Parkway, Ste. 100, Frisco
Type of work: new construction
Timeline: Jan. 31-June 15
Estimated cost:$400,000
Prosper ISD Elementary School No. 18: northwest corner of Alvira Drive and Hillcrest Road, Frisco
Type of work: new construction
Timeline: Feb. 25, 2023-June 25, 2024
Estimated cost: $35 million