Curious about the future of development in Frisco? There are multiple multi-million dollar projects slated to begin in 2023 throughout the city. The following projects’ costs add to nearly $337 million. See some of the largest upcoming projects in Frisco below. The following projects have been filed through the Texas Department of Licensing and Regulation. The following information may be subject to change.
FCS Office Interiors: 10401 John W Elliott Drive, Ste. 100, Frisco
Type of work: New construction
Timeline: June 1, 2023-Oct. 31, 2023
Estimated cost: $2 million
Frisco Flyers Addition: Northwest corner of All Stars Ave. and John Elliott Drive, Frisco
Type of work: New construction
Timeline: Jan. 1, 2023-June 30, 2023
Estimated cost: $4.5 million
Heritage Business Park: 11691 Independence Parkway Building 100, Frisco
Type of work: New construction
Timeline: Jan. 1, 2022-Dec. 1, 2023
Estimated cost: $1 million
The following project is part of the Fields development project in Frisco and has yet to determine an address. The project is a 4 story, 257-unit multifamily project with leasing and fitness amenities.
North Fields Block A, Lot 1: TBD
Type of work: New construction
Timeline: March 20, 2023-Dec. 31, 2024
Estimated cost: $73 million
The Star: 17 Cowboys Way, Frisco
Type of work: Renovation/alteration
Timeline: Dec. 1, 2022-Dec. 31, 2023
Estimated cost: $2.8 million
Jefferson Railhead: Located off of the Dallas North Tollway, bordered by Eldorado Parkway on the north and Main Street
Type of work: New construction
Timeline: Jan. 1, 2023-Jan. 1, 2025
Estimated cost: $99 million
Frisco Police Department: 7200 Stonebrook Pkwy, Frisco
Type of work: New construction
Timeline: Dec. 12, 2022-Nov. 17, 2023
Estimated cost: Approximately $6.8 million
Hall Park: 3010 Gaylord Parkway, Frisco
Type of work: New construction
Timeline: Dec. 1, 2022-Dec. 1, 2023
Estimated cost: $10 million
The next three projects are part of the Project X development for urban living units. The projects have yet to determine an address.
Project X - Urban Living Units: TBD
Type of work: New construction
Timeline: Jan. 30, 2023-May 29, 2026
Estimated cost: Approximately $7 million
Project X - East: TBD
Type of work: New construction
Timeline: Jan. 30, 2023-May 29, 2026
Estimated cost: Approximately $54.8 million
Project X - West: TBD
Type of work: New construction
Timeline: Jan. 30, 2023-May 29, 2026
Estimated cost: Approximately $76 million