Project: The street is receiving utility installations and pavement replacement along with the replacement of pavement, curb, gutter, and any sidewalks from Crescent Street to Panhandle Street.
Update: Water main and sewer lateral installation continue on Alice Street with tie-ins scheduled for the beginning of February. The estimated completion date for the utility installation is Jan. 30, not the original Jan. 9 completion date.
- Timeline: May 2025-June 2026
- Cost: part of $50 million road update for 2019 Bond Neighborhoods 2 & 6 project
- Funding source: city of Denton 2019 Bond Program
Denton StreetProject: The road has been closed due to reconstruction of the street and replacing water and sewer lines from Hickory Street to Congress Street.
Update: Gas line work from Atmos has delayed the city’s construction on Denton Street. This delay is currently estimated to last until mid-March, with roadway reconstruction to follow.
- Timeline: June 2025-March 2026 for utility work
- Cost: part of $50 million road update for 2019 Bond Neighborhoods 2 & 6 project
- Funding source: city of Denton 2019 Bond Program
Eagle Drive