Check out details on three road projects in McKinney underway or set to start within the next year. This list is not comprehensive.

Upcoming projects

1. Medical Center Drive improvements

Project: Reconstruction and widening of Medical Center Drive between Frisco Road and Spur 399 as a four-lane divided roadway. The road is currently three lanes, undivided.

Update: McKinney City Council awarded a construction contract for the project Sept. 16. Construction is expected to begin before the end of the year.
  • Timeline: November 2025-late 2026
  • Cost: $5.2 million
  • Funding Source: city of McKinney
Ongoing projects


2. Virginia and Throckmorton infrastructure improvements

Project: Reconstruction of Virginia Street between SH 5 and Murray Street, and Throckmorton Street between Lamar and Louisiana streets. The project includes waterline, sanitary sewer, storm sewer, illumination, hardscape and landscape improvements, as well as a roundabout at the intersection of Virginia and Throckmorton streets.

Update: Sidewalk construction, illumination and landscaping work are ongoing. Throckmorton Street has been opened to northbound and southbound traffic, including through the roundabout at Virginia Street. Virginia Street remains closed between SH 5 and Main Street.
  • Timeline: March 2024-October 2025
  • Cost: $14 million
  • Funding source: city of McKinney
3. US 380 and Community Avenue intersection improvements

Project: Improvements are being made at the intersection of US 380 and Community Avenue. Plans include adding dual left-turn lanes to eastbound and westbound lanes, a southbound right-turn lane and traffic signal improvements.


Update: Traffic signal construction is nearly complete. Relocation of city and franchise utilities is underway. Roadway construction is expected to begin in the next few months.
  • Timeline: March 2025-mid 2026
  • Project Cost: $5.6 million
  • Funding Source: city of McKinney, Texas Department of Transportation