Check out details on 3 projects underway or recently completed at McKinney National Airport. This list is not comprehensive.
Projects underway
1. Taxiway A realignment and rehabilitation
Project: Realignment of the taxiway to widen a portion of Taxilane A, rehabilitation of concrete along the taxiway and creation of new connectors between Taxiways A and B.
Update: The first phase of the project is in the midfield runway area, and has seen concrete pouring completed. Work on drainage, light and construction of the midfield wind indicator is underway. Taxiway A3 will be opened following completion of that work, and Taxiway B3 will be permanently closed. The project’s second phase on the south end of the runway area will commence in spring 2026.
- Timeline: Sept. 2024-Oct. 2025 (phase one); March 2026-March 2027 (phase two)
- Cost: about $18.5 million (all phases)
- Funding source: Texas Department of Transportation grant funds
Project: Extension of the airport’s roughly 7,500-foot runway by an additional 500 feet on the north end.
Update: Grading and earthwork is underway, including drains to accelerate soil settlement. Following a 9-month soil settlement period, construction on the extension will begin.
- Timeline: Feb. 2025-Oct. 2026
- Cost: $30.45 million
- Funding source: Collin County, North Central Texas Council of Governments
3. Two airport west side buildings
Project: A new U.S. Customs and Border Protection facility in the airport’s midfield portion and a new corporate hangar at the south end of the airport.
Update: A certification of occupancy has been issued for the custom’s building, and U.S. Customs officials are finalizing a move-in date. A certificate of occupancy has also been issued for the hangar, and it is currently occupied.
- Timeline: March 2024-April 2025
- Cost: about $22.99 million (combined single project)
- Funding source: City of McKinney certificate of obligation bond funds