Doctors Urgent Care: 2660 Forest Vista Dr., Flower Mound
Type of work: new construction
Timeline: May 12-Oct. 19
Estimated cost: $1.3 million
Welch Office Building: 118 Lynn Ave., Building 800, Lewisville
Type of work: new construction
Timeline: June 15, 2022-Feb. 17, 2023
Estimated cost: $1.6 million
Lakeside Terranea: 2800 Lakeside Parkway, Flower Mound
Type of work: new construction
Timeline: June 1, 2022-April 30, 2024
Estimated cost: $110 million
Boxes by Slate: State Hwy/ 121, 700 feet northeast of Arcadia Way, Lewisville
Type of work: new construction
Timeline: June 1-Nov. 1
Estimated cost: $5 million
Wild Fork Food: 5850 Long Prairie Road, Flower Mound
Type of work: renovation/alteration
Timeline: May 2-Oct. 12
Estimated cost: approximately $2.4 million