The revision supports future phases of the Terminal F expansion, but does not impact the anticipated opening of Phase 1 of Terminal F in 2027, according to the presentation.
The new contract with Innovation Next+ is now $1.7 billion, and the current contract was extended by 379 days. The new projected end date for the work is Aug. 29, 2028.
The details
According to the airport website, Innovation Next+ is composed of Archer Western Construction, Turner Construction Company, Phillips May Corporation, H. J. Russell & Company and Carson Industries as builders and with PGAL, Gensler and Muller2 as design team members. That is the same group that is working on the Terminal F expansion.
The change order calls for the construction of earthworks, structure and building envelope to expand the concourse capacity for future passenger processing and concessions areas of Terminal F. A subsequent board action will address the remaining core and shell components, according to board documents.
During the November and December meetings, additional work on Terminal F and the Skylink Station was approved, totaling nearly $200 million, according to previous reporting.
Zooming in
Atrius Wayfinder, previously LocusLabs, was given a $1.8 million contract to upgrade the DFW Airport mobile app.
The Oakland, California-based company will add enhanced indoor navigation and wayfinding for users. It will also provide the ability to generate heat maps, dwell-time analysis for future planning by concessions and customer experience in the airport, according to board documents
Also on the agenda
Relay, a travel convenience store at Gate 22 in Terminal D, will be closed due to a checkpoint expansion project.
Paradies Lagardere will receive $169,295.10 for the lease termination, according to board documents.