Ongoing
1. Mahard Parkway construction
Project: Mahard Parkway is being constructed, and it will be six lanes. The roadway will span PGA Parkway to US 380 and will border the Firefly Park development.
Update: The project is under construction and is expected to be completed at the end of next year.
- Timeline: late 2024-late 2026
- Cost: $11.03 million
- Funding source: city of Frisco
Project: An intersection is being added to Hillcrest Road at Eldorado Parkway. The project cost will be reimbursed by the developer, according to the city’s Capital Improvement Projects website.
Update: The design phase for the project ended in early 2025 and construction
- Timeline: early 2024-early 2026
- Cost: $5.99 million
- Funding source: city of Frisco
Project: The road is being reconstructed as a 26-foot-wide concrete road from North County Road to Rogers Road. Reconstruction will include a drainage ditch and drainage system improvements and roundabouts built at two intersections along the road.
Update: Design plans are approximately 90% complete and construction is expected to begin in 2026.
- Timeline: 2025-2027
- Cost: $3.7 million
- Funding source: city of Frisco
Project: Lebanon Road will be widened from a four-lane roadway to a six-lane divided roadway from FM 423 to Todd Drive. Improvements include pavement reconstruction, bridge repair, drainage improvements and street light replacement, among others.
Update: City council awarded a contract for construction in October and construction was anticipated to begin in December 2025.
- Timeline: October 2025-late 2027
- Cost: $22.99 million
- Funding sources: city of Frisco, external funding
Project: The roadway will be reconstructed from an existing two-lane asphalt road to a six-lane, divided concrete roadway from Preston Road to Hillcrest Road.
Update: The road is under construction. Once complete, the improvements will include a new traffic signal, drainage upgrades, street lighting and the placement of a 36-inch water line.
- Timeline: 2024-mid 2026
- Cost: $31.10 million
- Funding source: city of Frisco, external funding
Project: The project spans Legacy Drive from Lebanon Road to Stonebrook Parkway and Stonebook Parkway from Legacy Drive to 4th Army Drive. The project will widen and reconstruct the roadway.
Update: The project’s design phase is expected to be completed by mid-2026.
- Timeline: mid 2026-late 2027
- Cost: $18 million
- Funding source: city of Frisco
Project: Teel Parkway will be widened from a two-lane roadway to a four-lane roadway from Stafford Middle School to Oliver Branch Road.
Update: The project’s design phase was completed in mid-2025 and construction is anticipated to be complete in late 2026.
- Timeline: September 2025-end of 2026
- Cost: $12.36 million
- Funding source: city of Frisco, external funding
Project: Roundabouts will be added along Frisco Street at Technology Drive, Sports Village Road, All Stars Avenue and Research Road.
Update: The project is in the design phase and will go out for construction bid next year.
- Timeline: mid 2026-early 2028
- Cost: $12 million
- Funding source: city of Frisco
Project: A new traffic signal is being installed at the Fields Parkway and Dallas Parkway intersection. The traffic light is adjacent to the new Universal Kids Resort theme park.
Update: The project is currently under construction.
- Timeline: mid 2025-mid 2026
- Cost: $350,000
- Funding source: city of Frisco
10. Panther Creek Parkway
Project: A new six-lane roadway has extended Panther Creek Parkway from Dallas North Tollway to Preston Road. The new roadway provides a continuous route across the city from FM 423 to Custer Road.
Update: The road was opened in late October with a new traffic signal at the intersection of Panther Creek Parkway and Universal Parkway
- Timeline: 2024-fall 2025
- Cost: $56.4 million
- Funding source: city of Frisco, Collin County