Upcoming
1. Legacy Drive updates
Project: Legacy Drive from Main Street to Panther Creek Parkway could see improvements.
Update: The project is in the early planning phase and details regarding project specifics are not yet available.
- Timeline: early 2027-mid 2028
- Cost: $13.6 million
- Funding source: TBD
Project: A new traffic light will be installed on Lebanon Road just west of Legacy Drive near the Kroger exit.
Update: The project is in the design phase, with bidding for the construction expected in fall 2025.
- Timeline: fall 2025-mid 2026
- Cost: $300,000
- Funding source: city of Frisco
Project: Legacy Drive from Lebanon Road to Stonebrook Parkway and Stonebrook Parkway from Legacy Drive to 4th Army Drive will be widened and reconstructed.
Update: The project is in the design phase, with construction bidding expected in 2026.
- Timeline: fall 2026-end of 2027
- Cost: $15 million
- Funding source: city of Frisco
4. Lebanon Road traffic light
Project: A new traffic light is being installed at the intersection of Lebanon Road and 4th Army Drive.
Update: The light poles have been installed and the project is nearing the end of construction.
- Timeline: end of 2024 to fall 2025
- Cost: $250,000
- Funding source: city of Frisco
Project: Lebanon Road will be widened from a four-lane divided roadway to a six-lane divided roadway from FM 423 to Todd Drive.
Update: The design phase of the project wrapped in mid-2025 and has moved to the construction phase.
- Timeline: fall 2025-mid 2027
- Cost: $22.98 million
- Funding source: city of Frisco, external funding
Project: A new traffic light is being installed on Stonebrook Parkway at the Walmart exit just east of FM 423.
Update: The light poles have been installed.
- Timeline: end of 2024-fall 2025
- Cost: $250,000
- Funding source: city of Frisco
Project: Panther Creek Parkway is being constructed from Dallas North Tollway to Preston Road. It will be a six-lane divided roadway once completed.
Update: The project is under construction and is expected to be completed at the end of the year.
- Timeline: 2024-end of 2025
- Cost: $56.4 million
- Funding source: city of Frisco, Collin County
Project: Hillcrest Road is expanded from two lanes to a four-lane divided roadway from Panther Creek Parkway to PGA Parkway.
Update: The project will increase the road's capacity, city officials said. Crews will soon begin paving work along with installing storm drains and street lights.
- Timeline: 2024-end of 2025
- Cost: $5.99 million
- Funding source: city of Frisco
Project: Main Street from BNSF railroad to North County Road and Fourth Street from Main Street to Elm Street is being reconstructed. The project will increase sidewalk widths, improve intersections and construct a pedestrian plaza.
Update: Traffic patterns continue to shift as construction progresses in the Rail District. It is on track for its 2026 completion.
- Timeline: early 2024-early 2026
- Cost: $20.54 million
- Funding source: city of Frisco