Work is expected to begin June 8 on the reconstruction of the bridge at Hwy. 290 and Barker Cypress Road as part of the ongoing Hwy. 290 expansion project.
The first phase of the project involves shifting travel lanes to the western half of the existing bridge, said Karen Othon, public information officer for the Texas Department of Transportation. Temporary pavement markings will be placed to allow for two lanes northbound and one lane southbound on the bridge.
"There will be lane closures on the bridge and on the main lanes to safely allow for demolition," Othon said. "Before June 8 we anticipate some intermittent closures to prepare for the traffic shift."
Othon said work has already begun on the project—crews have started on storm sewer installation along the frontage road of the highway. The demolition of the bridge is set to begin June 13.