1. Hwy. 290 Project D
Crews are working on westbound Hwy. 290 mainlanes west of Cypress Rosehill Road and the frontage road between Barker Cypress and Skinner roads in Cypress. A new eastbound exit ramp to Cypress Rosehill Road is expected to open in February, and the entrance ramp east of Spring Cypress Road will open later this spring. The project is part of an effort by the Texas Department of Transportation to widen Hwy. 290 between Loop 610 and FM 2920.
Timeline: February 2014-2018 Cost: $85.2 million Funding sources: TxDOT
2. Fairfield Place widening
Harris County Precinct 3 has finished work to widen Fairfield Place from two lanes to a four-lane boulevard from Cumberland Ridge Drive to Schiel Road in Cypress. Construction started Nov. 7, and the widened road opened to drivers Feb. 10.
Timeline: Nov. 7, 2016-Feb. 10, 2017 Cost: $1.07 million Funding sources: Harris County Precinct 3