1. Huffmeister Road widening
Severe flooding the Cy-Fair area in April has caused county officials to delay the opening until mid-June. Originally set to open in May, the project involves widening a two-lane asphalt road to a four-lane concrete boulevard.
Timeline: Summer 2015-June 2016 Cost: $3.1 million Funding sources: Harris County Precinct 3
[caption id="attachment_152649" align="alignright" width="220"]
Crews compact dirt on the Hwy. 290 outbound mainlanes approaching Telge Road. Once that work is done, the contractor will install concrete pavement on top to complete the mainlanes.[/caption]
2. Hwy. 290 Project D
Construction is ongoing to widen outbound Hwy. 290 mainlanes and construct new frontage roads between Telge and Mueschke roads. Officials with the Texas Department of Transportation hope to open the new roads in pieces with the entire project being open to drivers by the fall if weather permits. Once crews finish compacting dirt on outbound mainlanes, the contractor will begin to install concrete pavement.
Timeline: summer 2015-fall 2016 Cost: $85.2 million Funding sources: TxDOT