Several major construction projects are underway in Cy-Fair ISD with completion dates set throughout 2022. Elementary School No. 57 was included in the district’s 2014 bond, and the remaining following projects are part of the $1.76 billion bond program voters approved in May 2019. More than $258 million was dedicated to instructional and support facilities.

1. Exhibit Center renovations: A nearly 9,000-square-foot addition will bring the facility’s capacity from 600 to 1,593, including stadium-style and floor seating. The expansion also includes more restrooms and meeting space.
Estimated completion: April
Cost: $8.98 million

2. Brautigam Center addition: A career and technical education expansion project is underway at the Brautigam Center. The 12,000-square-foot addition will include labs and shop spaces. This campus serves students ages 16-21 who are catching up on graduation credits or working to graduate in less than four years.
Estimated completion: July
Cost: $6.64 million

3. Elementary School No. 57: A new two-story elementary school is under construction on a 16.7-acre tract in the Bridgeland area. The campus will feed into Smith Middle School and Bridgeland High School.
Estimated completion: August
Cost: $32.6 million