Contractors have begun laying out the traffic-control plan for the abandonment of the wastewater lift station on Tillery Street, which will determine when and which nearby lanes of traffic will be closed. A wastewater main line and a steel encasement pipe will be installed. Concrete manholes at the Boggy Creek Bed will also be constructed. Nearby residents and businesses may have limited access to driveways and parking during brief periods of the project.[/caption]
1. Gonzales Lift Station abandonment
Contractors have begun laying out the traffic-control plan for the abandonment of the wastewater lift station on Tillery Street, which will determine when and which nearby lanes of traffic will be closed. A wastewater main line and a steel encasement pipe will be installed. Concrete manholes at the Boggy Creek Bed will also be constructed. Nearby residents and businesses may have limited access to driveways and parking during brief periods of the project.
Timeline: April-December Cost: $1.3 million Funding source: Austin Water
[caption id="attachment_252665" align="alignright" width="220"]
The contractor has completed the installation of the storm drain and wastewater line along the west side of Colorado Street between Eighth and 10th streets. Work continues to complete the water line installation in the southwest quadrant of the Ninth Street intersection. The contractor plans to move into the south side of the Seventh Street intersection in early July to complete electrical improvements and street reconstruction.[/caption]
2. Colorado Street reconstruction
The contractor has completed the installation of the storm drain and wastewater line along the west side of Colorado Street between Eighth and 10th streets. Work continues to complete the water line installation in the southwest quadrant of the Ninth Street intersection. The contractor plans to move into the south side of the Seventh Street intersection in early July to complete electrical improvements and street reconstruction.
Timeline: November 2015-August 2017 Cost: $6 million Funding sources: 2012 Transportation and Mobility Bonds