Little Elm Trail extension[/caption]
1. Little Elm Trail extension The city of Cedar Park is continuing to fill existing gaps on Little Elm Trail between Lakeline Boulevard and US 183. The project includes right-turn lanes on southbound US 183, Lakeline and the existing portion of Little Elm. On Sept. 1, the road base, curb and gutter, sidewalk and first layer of asphalt through the Red Oaks subdivision was completed between Alexis Drive and Juliette Way, said Jennie Huerta, media and communications manager with the city of Cedar Park. The roadway will not be open to traffic until the end of the project, when all lanes will receive a new layer of asphalt and fresh striping. Between Lakeline and Juliette, the road bed is being prepared over the underground utilities. The right-turn deceleration lane on southbound US 183 at Little Elm is complete and awaiting approval by the Texas Department of Transportation to open for traffic, Huerta said.
Timeline: December 2015-early 2017 Cost: $7.06 million Funding sources: city of Cedar Park ($2.98 million); Cedar Park Community Development Corp., also known as the 4B Board ($550,000); Williamson County ($3.53 million)
2. East Whitestone Boulevard pass-through project The city of Cedar Park, TxDOT and Williamson County are collaborating on a project to rebuild East Whitestone Boulevard into a six-lane, divided roadway between Market Street and CR 175/Sam Bass Road. The project also includes a new intersection at Whitestone and Parmer Lane/Ronald Reagan Boulevard, which opened as a continuous-flow intersection Aug. 2. Additional work continues on RM 1431 between Parmer and Sam Bass, and the anticipated completion is in late September, Huerta said.