With a number of toll roads slated for completion in 2012, this year will represent the most miles added to the system since its debut in the region in 2007.
Hwy. 290 — Phase 1 of 3 of the Manor Expressway opens in 2012. The first phase includes four direct connectors between US 183 and East Hwy. 290 and a toll road from that intersection to Chimney Hill Road. Phase 2 extends the toll road to Giles Road and the third phase to Parmer Lane. The expressway will have six toll lanes and a three-lane nontolled frontage road in each direction.
- Timeline: Phased opening 2012–14
- Cost: Phase 1 is $73.4 million; total cost is $426 million
Toll 183A — A 5-mile extension of Toll 183A from north of RM 1431 to north of RM 2243 will be complete in 2012, making Toll 183A 11 miles long.
- Timeline: Spring 2012
- Cost: $105 million
Toll 130 — Segments 5 and 6 of Toll 130 will be complete in 2012 and will extend the highway 41 miles from the intersections of US 183, Toll 45 SE and Toll 130 to I-10 just east of Seguin. Currently, Toll 130 is 37 miles long and stretches from Georgetown to the intersection of those three highways.