Read about some of the latest updates on road and capital projects in League City. This list is not comprehensive.
Upcoming projects
Hobbs Road extension to FM 517
Project: This project includes constructing roughly 1,880 feet of a four-lane roadway. Initially, the two southbound lanes will be constructed, while the northbound lanes will be built at a later date.
Update: The project is in the Texas Department of Transportation permitting and right-of-way acquisition phase. Two of five parcels have been acquired, and the remaining are in process. The TxDOT permit could be in hand by the end of April.
- Timeline: bid schedule planned for summer 2026 unless issues with right-of-way acquisition arise
- Cost: CIP project budget is $10.34 million (project budget), with Galveston County contributing $2 million toward roadway construction
- Funding source: city funds and Galveston County
Maple Leaf intersection improvements
Project: The project includes adding a traffic signal to the Maple Leaf intersection of League City Parkway.
Update: The project is currently out for bids.
- Timeline: construction award is planned for May 2026 and construction phase to begin summer 2026 and slated completion at the end of 2026
- Cost: $790,000
- Funding source: capital projects funds from city
Ongoing project
Drainage improvements for FM 518 at Wesley Drive
Project: This is a drainage improvement project consisting of the installation of large pipes, storm boxes and inlets along and across FM 518 and Wesley Drive to improve drainage at the intersection area.
Update: Construction started at the end of March.