After design delays stalled the city-led project, Bastrop drivers could soon see extension work begin on a portion of Blakey Lane aimed at easing traffic congestion and improving access near Burleson Crossing East.
The gist
City Council approved a developer reimbursement agreement June 23 that allows BEBD Frontage Road LLC—the developer of Burleson Crossing East—to spearhead the extension, with the city reimbursing eligible costs during construction.
The Burleson Crossing East development runs adjacent to the proposed extension and has welcomed several new restaurants, businesses and clinics this year.
The cost
According to the cost estimate, the work includes the construction of a 375-linear-foot extension of Blakey Lane, along with the installation of waterlines.
Per the agreement, the city will reimburse the developer up to $690,000 for eligible costs through a monthly certification and payment process throughout construction.
Some context
Under a 2023 agreement, the city was responsible for building the extension; however, portions of the project have been delayed in the design phase as officials decide between extension and roundabout options.
City officials said the pivot will provide a way to move the work forward.
What’s next
Work must be completed within 18 months, or no later than December 2027.