Get the latest on three transportation projects in Bastrop and Cedar Creek—including a paused street rehabilitation project on Wilson Street, the upcoming repaving of South Pope Bend and two new four-way stops on Carter Street.
Upcoming
1. Wilson Street rehabilitation
Project: Plans include asphalt repair, milling, overlays, base repair and traffic control, with an optional tie-in at Wilson and Buttonwood streets.
Update: Bastrop Streets Director Lance Dodge said part of the project was finished in July between Farm and Cedar streets; however, the remainder of the project is on hold until 2027—following major construction work at the River Terrace subdivision.
- Timeline: 2027
- Cost: $462,400
- Funding source: 2026 Street Rehabilitation Fund
Upcoming
2. South Pope Bend repaving
Project: Plans include removing 7 inches of existing asphalt and repaving 1.5 miles on the roadway.
Update: Bastrop County commissioners will consider a contract with Asphalt Inc. on July 20. Officials hope to have the work finished before Aug. 12, ahead of Cedar Creek students returning to school.
- Timeline: 10 calendar days from start; work must be completed before nearby Cedar Creek students return to school Aug. 12
- Cost: $952,782.50
- Funding source: Bastrop County Precinct 1 budgeted funds
Completed
3. Carter Street four-way stops
Project: Four-way intersections were created to reduce speeding drivers near the Piney Creek Bend subdivision.
Update: Bastrop City Council OK’d the work at a June 23 meeting, and the intersections were completed by July 8.
- Timeline: July 8-9
- Cost: $1,600
- Funding source: city of Bastrop budgeted funds