Current situation
Major and minor construction projects, turf field replacements, track resurfacing and technology replacements are underway in RRISD, as the district gets moving on bond projects funded through three 2024 ballot initiatives. Administrators provided an update on these projects in an Aug. 21 board meeting.
The details
While every campus in the district is touched by the 2024 bond, major projects underway in the district include:
Renovation of former Spectrum building into career and technical education center
- Budgeted: $51.7 million
- As of August update, phone network installed with dedicated fiber-optic internet service to come. A contractor for the project is tentatively scheduled for fall board consideration pending completion of the district's master plan.
- Anticipate 12 months of permitting before construction phases.
- Budgeted: $60.9 million
- Contractor scheduled for September board consideration, with site investigation and preliminary design in progress. The district will begin the permitting process once design is complete.
- Anticipate 12 months of permitting before construction phases.
- Budgeted: $459,523
- Contractor scheduled for September board consideration, with site investigation and preliminary design in progress. The district will begin the permitting process once design is complete.
- Anticipate six to nine months of permitting before construction phases.
- Budgeted: $7 million
- Contractor scheduled for September board consideration, with site investigation and preliminary design in progress. The district will begin the permitting process once design is complete.
- Anticipate six to nine months of permitting before construction phases.
- Budgeted: $11.58 million
- Contractor scheduled for spring board consideration, with site investigation and preliminary design underway.
- Anticipate 12 months of permitting before construction phases.
- Budgeted: $30.6 million
- Contractor slated for fall or winter board consideration. Site investigation and preliminary design are in progress.
- Anticipate six to nine months of permitting before construction phases.
- Budgeted: $133 million
- Contractor set for spring board consideration pending completion of the district's master plan.
- Anticipate six to nine months of permitting before construction phases.
- Budgeted: $21.4 million
- Contractor slated for fall or winter board consideration depending on completion of the design plan.
- Anticipate 12 months of permitting before construction phases.
- Budgeted: $12.96 million
- Contractor selection set for fall or winder board consideration based on design plan completion.
- Anticipate 12 months of permitting before construction phases.
How we got here
In November, RRISD voters approved three of four propositions making up $932 million in investment for capital assets within the district.
The $998 million making up the full proposal was narrowed by trustees, district staff and RRISD's Citizens Bond Committee, chaired by Fabian Cuero and Lindsey Ledyard, from an original $1 billion-$1.5 billion proposal to address several areas of needed maintenance to capital assets within the district.
What else?
Administrators also debuted the district's new interactive bond tracker, which maps projects and provides a breakdown of how bond funds are being used on selected campuses.