David Hernandez Ministries: 1250 S. AW Grimes Blvd., Ste. 100, Round Rock
Type of work: renovation/alteration
Timeline: Feb. 7, 2022-Feb. 7, 2023
Estimated cost: $550,000
Scope of work: remodel of a newly demised tenant space
Kohl’s: 2101 Autumn Slate Drive, Pflugerville
Type of work: new construction
Timeline: May 1-Oct. 16
Estimated cost: $3.4 million
Scope of work: new Kohl’s department store
Pecan Central Office Park: 105 Rex Kerwin Court, Pflugerville
Type of work: new construction
Timeline: Feb. 1-Aug. 1
Estimated cost: $1.2 million
Scope of work: new construction of two single-story professional office buildings and related site work; buildings are 3,865 square feet and will total 7,730 square feet when fully completed
Oncor Service Center-Williamson County: 3487 CR 100, Ste. 100, Hutto
Type of work: new construction
Timeline: Dec. 15,-Nov. 30
Estimated cost: $8 million
Scope of work: construction of a new single-story office building with exterior, coverage storage, and parking canopies
45 Crossing - Suite 100 Ready Spaces: 2700 Louis Henna Blvd., Ste. 100, Round Rock
Type of work: renovation/alteration
Timeline: Jan. 1-April 1
Estimated cost: $325,000
Scope of work: new interior buildout in an existing shell building