AutoZone: 400 W. Palm Valley Blvd., Round Rock
Type of work: renovation/alteration
Timeline: Feb. 17-April 3
Estimated cost: $900,000
Scope of work: remodel of an existing 26,578-square-foot building
Target: 1870 Limestone Commercial Drive, Ste. 100, Pflugerville
Type of work: renovation/alteration
Timeline: May 23-Sept. 2
Estimated cost: $953,428
Scope of work: interior renovation
Dr. Philip Matson, DDS: 3100 RM 1431, Ste. 104, Round Rock
Type of work: new construction
Timeline: Jan. 3-March 4
Estimated cost: $399,750
Scope of work: first generation interior finish out of a new shell building
JJ’s Wok in H-E-B Plaza: 1420 W Wells Branch Pkwy., Bldg. 200, Ste. 280, Pflugerville
Type of work: renovation/alteration
Timeline: Nov. 15-Feb. 21
Estimated cost: $150,000
Scope of Work: interior build out of a 2,275-square-foot restaurant.
Kohl’s Department Store: 2101 Autumn Slate Drive, Pflugerville
Type of work: new construction
Timeline: Start date is Jan. 17, 2022, and completion date is August 30, 2022
Estimated cost: $3,000,000
Scope of Work: site construction grading, erosion control, site utilities, paving and landscaping