Learn more about ongoing and future road projects in Hutto and Pflugerville.
Project: The road will be widened to four lanes from Moorlynch Avenue to Weiss Lane.
Update: Full utility design was completed in May.
- Timeline: completion expected in March 2028
- Cost: $36 million
- Funding source: city bond funds