Learn more about ongoing and future road projects in Hutto and Pflugerville.
Project: The road will be widened to four lanes from Moorlynch Avenue to Weiss Lane.
Update: Full utility design was completed in May.


Local · Trusted · Free
The Morning Impact — your neighborhood's most important stories, delivered every morning.







Learn more about ongoing and future road projects in Hutto and Pflugerville.
Project: The road will be widened to four lanes from Moorlynch Avenue to Weiss Lane.
Update: Full utility design was completed in May.
Project: The road will be reconstructed with pavement, curb, drainage, sidewalk and streetlight improvements.
Update: The project went to bid in May.
Project: The road will be widened to three lanes and extended to connect to SH 45.
Update: The city anticipated receiving 60% of design plans by the end of June.
Project: The road will connect to SH 130 Frontage Road.
Update: The completion date was extended to August.
Project: The project will reconstruct CR 199 from CR 132 to FM 1660 South.
Update: Funding will be allocated in 2028
Project: New turn lanes and signals will be added to the intersection of FM 1660 South and Hwy. 79.
Update: Design is complete.
Old Town parking and traffic improvements
Project: The city is converting downtown streets into one-way traffic.
Update: Main Street was converted to a one-way in April.