Pecan Street Gas Station—16212 Impact Way, Pflugerville
Type of work: New Construction
Timeline: Dec. 1-Oct. 1, 2022
Estimated cost: $450,000
Scope of work: a new construction of a 1-story 5,954 sf retail building
AW Grimes Retail—2720 AW Grimes Blvd., Round Rock
Type of work: New Construction
Timeline: Nov. 1-Dec. 1, 2022
Estimated cost: $6.8 million
Scope of work: Construction of two one-story cold dark shell buildings with associated site work.
AHS Multifamily Residential Buildings and Clubhouse—550 Exchange Blvd., Hutto
Type of work: New Construction
Timeline: Feb. 2, 2022-Feb. 2, 2023
Estimated cost: $26.1 million
Scope of work: Multifamily of approx. 204 apartment units, leasing office, clubhouse, indoor amenities area, and exterior amenities.
Ovivo—1120 New Technology Blvd., Hutto
Type of work: New Construction
Timeline: Jan. 1, 2022-Sept. 1, 2022
Estimated cost: $11,150,167
Scope of work: This project involves the construction of a new tilt-up building to contain administrative office and manufacturing spaces.
Creekside Dessau—16201 Dessau Road, Pflugerville
Type of work: New Construction
Timeline: Jan. 1, 2022-Jan. 1, 2023
Estimated cost: $13 million
Scope of Work: New mixed use retail/apartment building