2. On the southbound side, that lane will not be ready until early November Although the opening is “fast-approaching at this point,” the southbound lane might not open until early November, Pustelnyk said. Crews are still milling existing pavement on the southbound side and will soon start level-up paving that will prepare the roadway for the final layer of pavement. 3. The underpasses, which are pretty much complete, are not Harvey-proof Although the agency reported no flooding during Hurricane Harvey, if the Austin region experiences Harvey-level rains of several inches per hour, those underpasses could flood. “The underpasses handled the hurricane event very well,” Pustelnyk said. “The good news with these underpasses is that they are at a higher elevation than where they drain to. Other than a rain that exceeds the ability of the inlets and the pipes that handle it, it will drain well.” The Mobility Authority has also installed a flood detection system that would automatically notify the agency of any standing water so it could close the underpasses, which drain to Johnson Creek, Pustelnyk said. “I feel personally much better about the drainage than I did maybe going in,” Mobility Authority Executive Director Mike Heiligenstein said. “I now have the confidence that they can handle it.” 4. Tolls could be in the $2 range Currently, the peak toll on the open northbound section is around $0.75, but that is because that section is the least traveled portion of the MoPac project, Pustelnyk said. Agency research indicates the total cost of the toll for driving the entire length of the express lane in one direction could be in the $2 range, he said. Once the lanes open, the Mobility Authority will use sensors installed along the corridor to monitor traffic flow and traffic counts. The tolling system has already been installed, and the agency is testing it. 5. Remaining landscaping work could be pulled out of the project under a separate contract In May, the agency already pulled some work from the MoPac project to manage under separate contracts for time and cost savings. Remaining landscaping work could also be completed in a similar fashion, the board discussed Wednesday. “A big part of [the project] is making sure those underpasses are reconnecting the east and west sides of MoPac in a way that is aesthetically pleasing, good for pedestrians and bicycles and is good for the community,” Heiligenstein said. “That’s going to be a definite upgrade. These elements are really crucial for, I think, a successful project at the end of the day." Disclosure: Amy Ellsworth, general manager for Community Impact Newspaper’s Round Rock-Pflugerville-Hutto edition, was appointed in February to the Central Texas Regional Mobility Authority board of directors, serving a two-year term through Jan. 31, 2019.There are signs all over that we are getting close to opening. Hang in there! pic.twitter.com/zNftmfxKDz
— MoPac Project (@ImproveMopac) September 1, 2017