Curious about which new businesses, restaurants and facilities are coming soon or underway in your backyard and beyond? Our commercial project roundup helps identify what is being built in the community. The following commercial permits have been filed recently in the Lake Travis area under the Texas Department of Licensing and Regulation. All information, including cost and timeline, is subject to change.

Fidelity Fitness Center: One Destiny Way, Westlake

Type of work: renovation/alteration

Estimated cost: $2.47 million

Timeline: May 1-Aug. 31


Scope of work: interior renovation of existing fitness center

Carbon Health, Shops at the Galleria: 12918 Shops Parkway, Ste. 100, Bee Cave

Type of work: renovation/alteration

Estimated cost: $400,000


Timeline: Aug. 15-Nov. 21

Scope of work: interior build-out of tenant suite for medical clinic

Cava: 701 S. Capital of Texas Hwy., Ste. G750, West Lake Hills

Type of work: renovation/alteration


Estimated cost: $175,000

Timeline: April 1-Sept. 1

Scope of work: interior renovation

Sculpture Garden Pedestrian Bridge: Lohmans Crossing Road and Cross Creek, Lakeway


Type of work: new construction

Estimated cost: $134,000

Timeline: June 27-Aug. 31

Scope of work: approximately 513 linear feet of 8-foot concrete trail, including 20-linear-foot pedestrian bridge over Hurst Creek


Riley’s Ranch Pet Spa: 15839 W. Hwy. 71, Bee Cave

Type of work: new construction

Estimated cost: $3 million

Timeline: May 2, 2022-May 1, 2023

Scope of work: new construction of an animal boarding facility



Westlake Entrada: 63 Tarragona Drive, Westlake

Type of work: new construction

Estimated cost: $500,000

Timeline: May 16-Sept. 16

Scope of work: tenant finish-out of a restaurant space

Lakeway Medical Village: 312 Medical Parkway, Lakeway

Type of work: new construction

Estimated cost: $3.1 million

Timeline: March 1-Dec. 15

Scope of work: tenant improvements for the first floor lobby and the second floor

Summer Moon Coffee Shop; 15511 W. Hwy. 71, Bee Cave

Type of work: new construction

Estimated cost: $325,000

Timeline: Feb. 7-Aug. 1

Scope of work: new build-out to existing building

Total Care Primary Care: 1945 Medical Drive, Ste. 150, Lakeway

Type of work: renovation/alteration

Estimated cost: $150,000

Timeline: May 1-Sept. 30

Scope of work: first time interior tenant finish-out

Watkins Insurance Group: 3500 S. FM 620, Ste. C, Bee Cave

Type of work: new construction

Estimated cost: $1.2 million

Timeline: Aug. 1-Sept. 15

Scope of work: ground-up construction, including the interior finish-out of a 4,470-square-foot building for office use