Project: A 10-foot paved shared-use path is planned along Lakeline Boulevard between New Hope Drive and Little Elm Trail to improve pedestrian and bicycle connectivity.
Update: Design is 90% complete. Plans have been revised to modify an existing roadway bridge rather than construct a new pedestrian bridge, with final design and permitting ongoing.
- Timeline: construction start date TBD-expected completion winter 2026
- Cost: $10.5 million
- Funding source: Texas Department of Transportation
2. RM 1431 road and intersection improvementsProject:
Road improvements are planned from New Hope Drive to Bagdad Road and also at the intersection of RM 1431/Whitestone Boulevard and 183A Toll, both in an attempt to improve traffic flow and enhance safety for drivers, pedestrians and cyclists.
Update: The project is moving into preliminary engineering and design of the intersection. The road improvements schematic has been approved by TxDOT and is awaiting funding approval and environmental clearance.
- Timeline: construction start date TBD-expected road completion winter 2027, intersection winter 2026
- Cost: $11.9 million for road, $15.9 million for intersection
- Funding source: city of Cedar Park, Mobility Authority, Surface Transportation Block Grant