The Great Greek—3101 E. Whitestone Blvd., Ste. 100, Cedar Park
Type of work: new construction
Estimated cost: $420,000
Timeline: Aug. 8-Oct. 14
Scope of work: tenant fit out within new shell building for use as a restaurant
Next Level Urgent Care—1500 E. Whitestone Blvd., Ste. 600, Cedar Park
Type of work: renovation/alteration
Estimated cost: $467,360
Timeline: July 11-Nov. 21
Scope of work: renovation of existing tenant lease space for new clinic
Ocean’s Golfer—200 Buttercup Creek Blvd., Ste. 109, Cedar Park
Type of work: renovation/alteration
Estimated cost: $300,000
Timeline: July 30-Oct. 30
Scope of work: interior remodeling by tenant
Floor King—1200 BMC Drive, Bldg. 1, Ste. 200, Cedar Park
Type of work: new construction
Estimated cost: $400,000
Timeline: July 1-Sept. 30
Scope of work: create office area in warehouse
Bell District Section 1—310 S. Bell Blvd., Cedar Park
Type of work: new construction
Estimated cost: $7 million
Timeline: Aug. 1, 2022-Jan. 31, 2023
Scope of work: construction of public streets and utilities for Section 1 of the Bell District; no vertical construction is proposed in these plans
Crystal Falls Retail—10921 Crystal Falls Parkway, Leander
Type of work: new construction
Estimated cost: $700,000
Timeline: July 1, 2022-Jan. 2, 2023
Scope of work: approximately 12,000 square feet of shell building only
Elementary School No. 6—Stamp Iron Avenue, Leander
Type of work: new construction
Estimated cost: $38 million
Timeline: May 15, 2022-Aug. 31, 2023
Scope of work: construction of a 120,580-square-foot elementary school in the city of Leander; project includes building, site work and infrastructure associated with building functionality
Editor’s note: This commercial permit could not be mapped.
Night Owl III—203 N. Brushy St., Leander
Type of work: new construction
Estimated cost: $280,000
Timeline: April 25, 2022-April 24, 2023
Scope of work: new bar building in a previously unoccupied location; includes architectural, interior design, structural, civil, electrical and mechanical work
Northline Town Square—400 Northline St., Leander
Type of work: new construction
Estimated cost: $3.1 million
Timeline: July 1, 2022-March 1, 2023
Scope of work: proposed project includes the construction of hardscape improvements; landscape improvements; two restroom facilities; a central pavilion; and association storm, water and wastewater improvements
Harmony Science Academy—3250 Hero Way, Leander
Type of work: new construction
Estimated cost: $13 million
Timeline: July 1, 2022-June 1, 2023
Scope of work: new construction for elementary school