Bastrop ISD experienced a nearly 30% increase in student enrollment in the past decade. With a projected 15,500 students expected to be enrolled in BISD schools by 2027-28, the district’s schools are undergoing numerous renovation and construction projects.

The following projects have been filed in the last month through the Texas Department of Licensing and Regulation. The following information may be subject to change.

Emile Elementary School: 601 Martin Luther King Drive, Bastrop
  • Type of work: renovation/alteration
  • Timeline: June 1, 2023-Dec. 1, 2024
  • Estimated cost: $2.6 million
Bluebonnett Elementary School: 416 FM 1209, Bastrop
  • Type of work: renovation/alteration
  • Timeline: June 1, 2024-Dec. 1, 2024
  • Estimated cost: $1.8 million
Lost Pines Elementary School: 151 Tiger Woods Drive, Bastrop
  • Type of work: renovation/alteration
  • Timeline: June 1, 2024-Dec. 1, 2024
  • Estimated cost: $1.8 million
Cedar Creek Elementary School: 5582 FM 535, Cedar Creek
  • Type of work: renovation/alteration
  • Timeline: June 1, 2024-Dec. 1, 2024
  • Estimated cost: $1.9 million
Red Rock Elementary School: 2401 FM 20, Red Rock
  • Type of work: renovation/alteration
  • Timeline: June 1-Dec. 1, 2024
  • Estimated cost: $1.8 million
Cedar Creek Middle School: 125 Voss Parkway, Cedar Creek
  • Type of work: renovation/alteration
  • Timeline: Sept. 1, 2023-Aug. 30, 2024
  • Estimated cost: $6.13 million
Bastrop Middle School: 725 Old Austin Highway, Bastrop
  • Type of work: renovation/alteration
  • Timeline: Sept. 1, 2023-Aug. 30, 2024
  • Estimated cost: $6.13 million
Bastrop Intermediate School: 509 Old Austin Highway, Bastrop
  • Type of work: renovation/alteration
  • Timeline: Sept. 1, 2023-Aug. 30, 2024
  • Estimated cost: $3.97 million
Cedar Creek Intermediate School: 151 Voss Parkway, Cedar Creek
  • Type of work: renovation/alteration
  • Timeline: Sept. 1, 2023-Aug. 30, 2024
  • Estimated cost: $3.97 million
Bastrop High School: 1614 Chambers St., Bastrop
  • Type of work: new construction
  • Timeline: June 1, 2023-Dec. 31, 2024
  • Estimated cost: $3.8 million