Editor’s note: This story was updated after publication to reflect that lanes on the Old Iron Bridge project are now open intermittently.
Local and state leaders are launching a wave of transportation projects across Bastrop County to address traffic congestion, improve roadway safety and prepare for continued regional growth.
This list is not comprehensive.
Upcoming projects
290 extension project
Project: Congestion will be reduced along 15 miles of Hwy. 290 between Hwy. 130 and Hwy. 95 South.
Update: A public survey concluded Oct. 10.
- Timeline: expected to complete first draft of schematic design mid-2026
- Cost: TBD
- Funding source: TBD
FM 812 improvement project
Project: FM 812 will be upgraded to increase safety, reduce congestion and improve mobility.
Update: The project spans from US 183 in Travis County to Hwy. 21 in Bastrop County.
- Timeline: expected to finalize design plans in spring 2026
- Cost: $145 million
- Funding source: Texas State Highway Fund
Hwy. 21 improvement project
Project: Approximately 7 miles of Hwy. 21 from County Road to Old Highway 20 will be expanded.
Update: Preliminary plans are for the corridor to become a four-lane divided highway with a grassy median.
- Timeline: schematic design and environmental study underway
- Cost: TBD
- Funding source: TBD
Ongoing projects
Blakey Lane extension
Project: Blakey Lane will be extended from Edward Burleson Lane to a proposed street called Reed Way, south from Reed Way to an intersection at Old Austin Highway, with roundabout options.
Update: The planning stage is 56% complete.
- Timeline: scheduled to begin construction May 25
- Cost: $7 million-$8 million
- Funding source: transportation impact fees, roadway maintenance fees, and water and wastewater fees
Farm, Linden and Water streets improvements
Project: Streets are being repaved along the primary sections of Farm, Linden and Water streets, including:
- Farm Street from Main Street to Wilson Street and from Main Street to Pecan Street
- Water Street from Gutierrez Street to north of Elm Street
- Linden Street from Carter Street to Hill Street
Update: Striping activities began Feb. 13, and Water Street was completed Feb. 17.
- Timeline: construction began in November
- Cost: $4.36 million
- Funding source: certificates of obligation series 2022 and 2023
Old Iron Bridge rehabilitation
Project: Rehabilitation will include a concrete deck, steel truss components, railing and decorative lights.
Update: East- and westbound lanes began opening intermittently March 5.
- Timeline: scheduled to conclude construction in late September
- Cost: $9.6 million
- Funding source: certificates of obligation series 2018, 2023 and 2025