Two widening projects along FM 1488 are underway, with one set to be completed in the third quarter of this year.
FM 1488 widening west of Magnolia
The Texas Department of Transportation’s widening of FM 1488 from the Waller County line to FM 1774 is 62% complete, according to a March 14 update. The project, which is widening FM 1488 from two to four lanes, began in November 2020 and is scheduled to be completed in the third quarter of 2023. Lindsey Construction Inc. was awarded the project.
Timeline: November 2020-third quarter 2023