At the Oct. 13 regular meeting, Tomball ISD board members authorized multiple material purchases and construction contracts totaling over $11 million and approved a slight name change for Creekside Park Jr. High School.
The discussion
TISD approved multiple material purchases and construction contracts using funds from the 2025 bond. As previously reported, TISD passed a $429.1 million bond package on May 3, 2025.
Approved projects using the funds include the Tomball High School HVAC Controls Replacement, with a project cost of $3.7 million. The approved projects also include athletic facility improvements for Tomball High School with a construction cost of $4.04 million and a contingency budget of $300,000.
TISD also approved a $2.73 million purchase of student Chromebooks and staff laptops using 2025 bond funds, along with new classroom technology devices that will cost $1.35 million.