At the Nov. 16 regular board meeting, the Magnolia ISD board of trustees approved the official name for Elementary School No. 10, as well as purchases to support the school's upcoming construction. 

The gist 

According to its website, MISD plans to construct Elementary School No. 10, funded by the recently passed 2026 bond program. The total cost for the project is estimated to be $54 million, and the school will open by August 2028. At the Nov. 16 regular meeting, the board formally voted to name the campus Kresston Elementary.

Alongside the new name, the MISD board voted to approve a building package for B&C Construction, which is overseeing the construction of the new campus. The total estimated cost of the package is $5.88 million, covering six main expenses: 

  • Temporary facilities: $10,000

  • Temporary fencing: $20,000

  • Stormwater pollution prevention plan: $28,000

  • Electrical underground: $232,707

  • Clearing, grubbing, building pad and grading: $835,000

  • Structural steel package: $4.04 million

Something to note

Tim Bruner, Magnolia ISD executive director of facilities, said that due to recent inflation, steel is one of the items in the package that has seen a major increase in price. Compared to a previous steel package the district purchased in 2023, the cost had increased by an estimated 36%-37% or $1 million.