The Texas Department of Transportation is preparing to install medians along FM 1092 from Hwy. 59 in Stafford to Hwy. 6 in Missouri City.
Construction will begin in January and last until July, according to a presentation by Assistant City Engineer Jeremy Davis during the Nov. 1 City Council meeting. Crews will be directed to start working at FM 1092 and Hwy. 59, and they will make their way south through Missouri City, Davis said.
TxDOT awarded a $2.4 million construction contract to SCR Civil Construction in September, according to city documents.
Since TxDOT first brought the project to Missouri City city staff in November 2020, the city has held public meetings to receive community feedback on the project. Several intersections of concern have been addressed during the process. However, even as the project went out to bid, a couple Missouri City City Council members objected to it.