Construction is underway on a project to upgrade Champions Drive from a two-lane asphalt road to a two-lane concrete paved section with improved drainage between FM 1960 and Cypress Creek. It is still on track for completion by April 5, 2020, Rocchi said. Timeline: Sept. 24, 2018-April 5, 2020 Cost: $13.3 million Funding sources: Harris County Precinct 4, Champions Municipal Utility District
TransportationSpring - Klein
Champions Drive upgrades underway between FM 1960, Cypress Creek