1. T.C. Jester Boulevard signal installation
Crews continue work on the signal installation at 10 intersections on T.C. Jester Boulevard between FM 1960 and FM 2920. The contractor, Third Coast Services, has completed the work between FM 1960 and Louetta Road, and the first four traffic signals were activated Sept. 14.
Timeline: March 2014-December 2015 Cost: $2.56 million Funding sources: Harris County Precinct 4, Texas Department of Transportation
2. Aldine Westfield Road widening
Harris County has awarded the construction contract for the widening of Aldine Westfield Road from East Louetta to Riley Fuzzel roads to Allgood Construction Company. Utility relocations are ongoing for the project, which will widen Aldine Westfield Road from a two-lane asphalt roadway to a four-lane thoroughfare. The county has scheduled a preconstruction meeting for the project, which has been given a 240-day construction contract.
Timeline: December-July Cost: $4.18 million Funding sources: Harris County Precinct 4