Recently Completed
1. Boudreaux Road realignment
Harris County completed the extension and realignment of Boudreaux Road near the intersection of Hwy. 249 and the Grand Parkway in June. Working with TxDOT and the Harris County Toll Road Authority, the county extended Boudreaux Road from 2,500 feet west of Hwy. 249 to Hwy. 249 and realigned the roadway from Hwy. 249 to 3,500 feet east of Hwy. 249. Timeline: Project was completed June 8 Cost: $3.6 millionFunding Source: Harris County
Project Updates
2. Holzwarth Road extension
The widening of Holzwarth Road from FM 2920 to Spring Stuebner Road in Spring continues. The southern section—expanding the road to a four-lane boulevard from FM 2920 to just north of Emerson Ridge—has been completed. Construction continues on the northern section from north of Emerson Ridge to Spring Stuebner Road, which includes four lanes and storm sewer system.