A five-year capital improvement plan and information on a new station were presented to the Harris County Emergency Services District No. 11 Board of Commissioners during its Nov. 17 regular meeting.
ESD 11 is the governing body responsible for providing emergency medical services throughout the district, which spans 177 square miles of north Harris County.
The projections
Commissioners received a five-year capital improvement plan, or CIP, from Chief Financial Officer Tony Farmer, outlining the district’s projected costs.
Farmer said while the management team has historically focused on the year ahead, he is hoping to implement long-range planning. The goal is to present a five-year CIP every year, he said.
Remounting ambulances, as well as purchasing new ones, is projected to cost about $6.2 million of the $8.56 million budgeted for fiscal year 2027. Remounting involves taking the patient care portion out of an older vehicle and installing it into a newer ambulance.
The highest projected cost for fiscal year 2028 is also for remounting ambulances, which is projected to cost about $2.6 million of the $7.7 million budgeted. Ambulance remounts are also expected to be the largest expense in fiscal year 2029, with a projected cost of about $1 million of the $1.13 million overall.
No projected costs are budgeted for fiscal year 2030. However, fiscal year 2031 is when ESD 11 is estimated to need 10 new ambulances, which is projected to cost about $4.4 million.
“I think it goes without saying that just because we budget, doesn’t mean we bought it,” Farmer said to the commissioners.
The board unanimously adopted the CIP, with the caveat that it is a living document and is subject to change.
Also on the agenda
A feasibility study looking at rebuilding Station 411 and a facilities building, both located on administration property, was also presented to commissioners.
Javier Guerrero, an assistant project manager with Martinez Architects, recommended during a presentation to the commissioners that the existing facilities building be replaced instead of renovated. Replacing it would be more affordable, he said.
As it stands, Guerrero said the building is “oversized for its function.”
“We just don’t think it’s worth bringing it to life,” Guerrero said.
Commissioner Dorothy Dalton said the building was a “money pit” and agreed it shouldn’t be renovated.
Guerrero also discussed rebuilding and redesigning Station 411, one of the district’s newest 24-hour mobile healthcare stations.
The station design includes two vehicle bays, four dorms and a club space that would feature five bunk beds, Guerrero said. The study also outlines a kitchen, dining area and day room for the station.
The building would be 4,511 square feet, and construction costs are estimated to be between $2.75 million and $3 million, Guerrero said. ESD 11 has projected the new station to cost $5 million, with the money budgeted for fiscal year 2028, according to the CIP.
Commissioners asked for a plan that would include an option to have the station closer to the road. Martinez Architects is expected to return next month with a design proposal for the station.
The board will hold its next meeting Dec. 22.