Several projects funded by the $498 million 2015 bond election will be completed this summer, said Robert Robertson, Klein ISD associate superintendent for facility and school services.
Klein Cain High School is in the final phases of construction and will open to students in August. The cost of the project was $185 million.
Site work on Intermediate School No. 10 was underway in May. The $46.4 million school will open in August 2018, Robertson said.
Construction of the $13.5 million Klein Forest Career Technical Education Center will begin in June, and the facility has a projected opening date of August 2018.