South Austin’s Baranoff Elementary School, located at 12009 Buckingham Gate Road, will see an estimated $651,100 of work to improve the campus’s roofs over the summer.
Austin ISD trustees ordered the district to negotiate a contract with Premier Metalwerks for the project, which was approved as a renovation in the district’s 2017 bond program. Premier Metalwerks was one of eight companies to place bids on the project.
While the project was originally budgeted for $1.1 million, the reduction in estimated cost is due to “the refinement of the project scope” to accurately reflect current needs, according to district documents. Work will include improvements to school gutters and downspouts, as well as the installation of a reflective coating that will extend the roof’s lifespan and the building's energy efficiency, according to the district.
Once a contract is approved, contractors will begin working on the project within 10 days, according to the contract.