During a June 15 City Council meeting, Kyle City Engineer Leon Barba provided updates on a number of road projects.
He told council members the roughly $9.2 million North Burleson Street improvements project was nearing completion and was expected to be finished in July or August. Some of the project’s features include a new storm system designed to handle five-year storm events, which have a 20% chance of happening in a given year; improved access to Burleson from side streets; improved sight distances; and reduced through traffic through the use of a cul-de-sac.
The roadway’s ditches were previously rated as being capable of handling two-year storm events, which have a 50% chance of occurring in a given year, according to the city.
Barba also updated City Council on the Windy Hill Drainage project, which he said was 65% complete. The north half of the road is under construction, with traffic routed onto the south half, but is expected to be complete in mid-July.