Curious about which new businesses, restaurants and facilities are coming soon or currently underway in your backyard and beyond? Our commercial permit roundup helps identify what is being built in the community. The following commercial permits have been filed recently in San Marcos, Buda and Kyle under the Texas Department of Licensing and Regulation. All information, including cost and timeline, is subject to change.
Harbor Freight: I-35 South Frontage Road, San Marcos
Type of work: new construction
Estimated cost: $850,000
Timeline: July 30-Oct. 30
Scope of work: shell building for a new Harbor Freight retail store
Alta Centerpoint: Commercial Loop, San Marcos
Type of work: new construction
Estimated cost: $1.5 million
Timeline: March 15, 2023-March 15, 2025
Scope of work: new construction of a 330-unit for-rent multifamily complex with a freestanding amenity area
7-Eleven: I-35 and Zell Dickinson, San Marcos
Type of work: new construction
Estimated cost: $800,000
Timeline: June 27, 2022-Jan. 24, 2023
Scope of work: new construction of a one-story convenience store with Laredo Taco and a car wash
Editor’s note: The location of this commercial permit could not be mapped.
Sherri Hill: 1795 Firecracker Drive, Buda
Type of work: new construction
Estimated cost: $800,000
Timeline: June 1-Aug. 4
Scope of work: construct office in a warehouse
Carvana: 2580 S. Loop 4, Buda
Type of work: new construction
Estimated cost: $3.27 million
Timeline: April 1-Nov. 30
Scope of work: a new premanufactured metal building for a Carvana sales office
Bobcat: 162 Commercial Drive, Buda
Type of work: new construction
Estimated cost: $1.3 million
Timeline: April 1, 2022-April 1, 2023
Scope of work: new Bobcat facility
Pet Paradise: 18900 I-35, Kyle
Type of work: new construction
Estimated cost: $4 million
Timeline: June 1, 2022-Feb. 28, 2023
Scope of work: ground-up masonry dog boarding and pet services facility, including vet clinic, grooming, day camp, indoor kennels and outdoor play areas
Plumb Creek Liquor: 4650 FM 1626, Kyle
Type of work: additions to existing building
Estimated cost: $160,000
Timeline: April 11-June 17
Scope of work: finish-out space for a new liquor store
Walk-On’s Restaurant: FM 1626 and Kohler’s Crossing, Kyle
Type of work: new construction
Estimated cost: $2 million
Timeline: June 1-Sept. 1
Scope of work: new building with related site work
Pollo Campero: Lot 10, Kyle Towne Center, Kyle
Type of work: new construction
Estimated cost: $2.11 million
Timeline: Aug. 1-Dec. 1
Scope of work: construction of a new Pollo Campero restaurant with related site improvements