Park35
Project: The Park 35 project, spearheaded by Investment and Development Ventures, LLC, will bring a six-building industrial park featuring 1.4 million square feet of warehouse space in the northern part of Schertz.
Update: The project has been under construction since April, with the expectation of completing the first four buildings by the end of 2024. Two of the four buildings are on schedule to be finished by September and October, while the remaining two are scheduled to be completed by the end of December. The second phase of the project will include the construction of two additional buildings.
Location: 23000 North I-35, Schertz
Timeline: April 2024-end of 2024 (Phase I)
Size: 1.4 million square feet
Core 5 Logistics Center
Project: Located at I-35 and Loop 1604, the project will feature four buildings constructed over two phases. Phase I of the project broke ground in 2022, with buildings designed to offer functionality to distribution tenants.
Update: Construction on buildings A and B is expected to be completed by the end of 2024, totaling approximately one million square feet. This would complete the first phase of the project.
Location: I-10 and Loop 1604, Schertz
Timeline: December 2022-December 2024 (Phase I)
Size: 1.8 million square feet
Corporate Drive Industrial Complex
Project: The project, located across from Selma City Hall, features two tilt-wall warehouse buildings. Ackerman & Co. broke ground on the project in 2023, with the estimated completion of the building construction in 2024.
Update: Partners Real Estate Group in June arranged a lease KW Automotive Inc. for around 75,000 square feet of space. The construction of the project has reached substantial completion. Both buildings include large glass openings and are ideal for owner users and multi-tenants.
Location: 9388 Corporate Drive, Selma
Timeline: 2022-24
Size: 511,000 square feet