Cibolo City Council on Oct. 11 approved authorization for the city manager to negotiate a contract with Henock Construction in the amount of $1.31 million to provide construction services for the public works expansion project, which will add a 4,000-square-foot expansion to the Cibolo Public Works Department's facility.
Funding for this project was included in the bond that passed in 2018, which was estimated at $650,000 for the construction.
According to Timothy Fousse, Cibolo's director of public works and capital projects, project costs have significantly increased over the last four years, which has led to the cost of the project being more than double the original estimation.
The city has around $600,000 available for the project and will be in search of additional funding sources as the project moves forward.