Update: The contractor is conducting field investigation and schematic development phase, with a 30% design schematic due this month.
- Timeline: will let in 2027 or 2028, depending on CAMPO funding schedule.
- Cost: $9.6 million for construction
- Funding source: combination of CAMPO and type B sales tax revenue
Eagles Nest extensionProject: The first phase of the extension will construct a four-lane roadway from Cypress Boulevard to Mays Street. The second phase will extend this four-lane road with two bridges over Chandler Creek and I-35. Future phases will extend the street further west to connect with Wyoming Springs Drive.
Update: The first phase of the project is in final environmental documentation and will go to bid for construction in early July. Construction is expected to start this fall.
- Timeline: TBD
- Cost: TBD
- Funding source: TBD
Roundabout at Sam Bass Road, Hairy Man Road IntersectionProject: A roundabout will be added to the intersection of Sam Bass and Hairy Man Roads to improve traffic flow and safety.