Round Rock officials took the first step in the process to rebid the Heritage Trail West project following bankruptcy of the original contractor during an Aug. 25 meeting.
City Council approved a resolution to rebid the project via competitive sealed proposal. This method will allow the city to select its next contractor for the project based on experience, financials and company history, among other factors.
Parks and Recreation Director Rick Atkins said the rebidding of this project will require the contractor selected to take over liability for the project, which he said is 20%-25% complete.
Currently, Halff Associates Inc. is engaged in an engineering contract to survey the existing project and determine its status, Atkins said during the Aug. 23 packet briefing.