Round Rock officials took the first step in the process to rebid the Heritage Trail West project following bankruptcy of the original contractor.
The Heritage Trail West project is funded by a 2013 bond and will connect the approximately 1-mile span between Chisholm Trail Road and North Mays Street along Brushy Creek. City Council approved a resolution to rebid the project through a sealed proposal at an Aug. 25 meeting.
Parks and Recreation Director Rick Atkins said the sealed proposal method will allow the city to select its next contractor for the project based on experience, financials and company history, among other factors.In February, Atkins told City Council that the original contractor, Pflugerville-based Ritter, Botkin Prime Construction Co., filed for bankruptcy in late 2021.
The city originally awarded the $7.3 million contract to Ritter, Botkin Prime Construction Co. in June 2020, and construction began on the trail segment in January 2021. At the Aug. 25 council meeting, Atkins said the rebidding guidelines will require the new contractor to take over liability for the trail upgrade project, which he said is already about 20%-25% complete.