1. Seton Parkway Extension completion
The extension of Seton Parkway will extend the roadway to Avery Nelson Boulevard as well as provide a connection to A.W. Grimes Boulevard to increase connectivity to Seton Medical Center Williamson and the higher education campuses. Crews are expected to complete the project in December.
Timeline: February 2014-December 2015 Cost: $2,730,288 Funding sources: city of Round Rock2. Picadilly Drive and Grand Avenue Parkway turn lanes
A. Grand Avenue Parkway will receive a turn lane at its intersection with Edgemere Drive. B. Picadilly Drive will receive a turn lane at its intersection with Central Commerce Drive to accommodate increased traffic from trucks. Drivers should anticipate construction delays between 9 a.m. and 4 p.m. as improvements are made to the intersection. Timeline: November 2015-February 2016 Cost: $456,016 Funding sources: city of Pflugerville
3. FM 685
The project is a major overhaul of FM 685 in Hutto between SH 130 and Hwy. 79. The road will be widened from two lanes to four lanes. Medians and turn lanes will be added, and two new bridges 12 feet higher than the current bridges will be built. The work is intended to improve traffic flow and safety. Timeline: October 2014-fall 2016 Cost: $15 million Funding sources: Capital Area Metropolitan Planning Organization, city of Hutto
4. Diverging diamond interchange
Work is substantially complete as of Nov. 23 on a new style of intersection called a diverging diamond at the University Boulevard/FM 1431 overpass of I-35 to alleviate traffic congestion in Round Rock. The new interchange will direct University left-turning traffic to the opposite side of the road for a short time.